The greens sodding project has come to its completion yesterday with the last 200 sq ft of sod being laid in the back of 5's green.  The topdressing on the old sodded areas has been completed this week as well.  Now we will continue the twice per week verticutting to remove the remaining Poa Trivilas to expedite the fill in of the bermudagrass.

The bunker project as far as the removal of the edge creeping that has been put on the back burner for the past two years is on its final holes.  Ideally we will only have hole 5 remaining for next week.  This will free the team up to address the maintenance of the bunkers in full force, meaning weed eating and simple edging.